Porter Township
HC 12 Box 461
Dingmans Ferry,
PA 18328
570-223-0447/570-775-7734 fax
Building Permit
Instructions
***Porter
Township Mandates the Pennsylvania UCC Building Code***
All applications and
building plans must be reviewed before the permits are issued. This
process may take 2 to 4 weeks and the applicant will be notified when
the permit is ready. At the time the permit is issued the building
permit fee must be submitted payable to Porter Township.
No job shall be started without a valid
building permit!
BUILDING PERMIT CHECKLIST:
ü Septic permit
ü Zoning permit
ü Workman’s’ Comp Information Form or Contractor’s proof of insurance
ü Plot Plan
ü 2 complete sets of building plans (including applicable plans & specifications)
ü Building sub-code with plan
ü Electrical sub-code with plan
ü Plumbing sub-code with plan
ü Mechanical sub-code with plan
PLEASE submit the package in its entirety to the Township Secretary
either by mail or in person.