A zoning permit is required
prior to the construction or placement or alteration of any
structure (in addition to a building permit).
NO JOB SHALL BE
STARTED WITHOUT A PROPER PERMIT.
Complete the application in full
including the tax
map # as found on your most recent property tax bill. Be
sure to sign the application. Incomplete applications will
be returned to the applicant.
ZONING PERMIT APPLICATION CHECKLIST:
·
ZONING PERMIT APPLICATION completely filled out including
signatures of owner and applicant (if other than owner).
·
SITE (PLOT PLAN) drawn to scale showing the property
boundaries, all
existing structures, proposed location of new construction
or alteration, location of well and septic. **Note-a survey
may be required.
The plot plan must show
setbacks or
distances from the proposed construction to the property
line. (Closest point of structure perpendicular to the
property line.)
·
COPY OF SEPTIC PERMIT if new construction or addition of any
bedrooms.
·
BUILDING PLANS: 1 copy drawn to scale to include a floor
plan profile with all rooms identified.
·
Appropriate Zoning Permit Fee payable to Porter Township.
Submit the entire package by mail to Porter Township or in
person to the Township Secretary.
ALLOW 7-14 BUSINESS DAYS FOR PROCESSING.
ZONING INSPECTIONS:
·
INITIAL INSPECTION-visual verification of submitted Plot
Plan
·
FINAL INSPECTION-Zoning Officer verification that project
was built and located as submitted.
CERTIFICATE OF OCCUPANCY:
·
No Certificate of Occupancy will be issued until the Zoning
Officer performs a satisfactory final inspection at the job
site.
·
ALL STRUCTURES require a CERTIFICATE OF OCCUPANCY.